top of page

Sycamore Cabin Building Progress

Click the first photo below to open the full gallery and view our construction timeline.

Land Survey

Completed 2019

Septic and water connections

Provided September 2021

Electrical supply

Provided May 2024

Drawings 

Completed March 2025

Contractor bids

Completed May2025

Building Permit

Granted June 2025.

Trees down

Started July 3, 2025

Driveway 

Started July 3, 2025

Excavation

Started July 6,  2025​

Concrete

Concrete footings and walls are up as of July 15, 2025.

Start of build

Schrock's Hilly Acres began on July 30, 2025

Rough-in electrical

On-site at Schrock's Hilly Acres, August/September.

Build complete

Scheduled for September 10, 2025.

Delivery Scheduled

Scheduled for September 11, 2025. 

Delivery

Schrock's Hilly Acres estimate September

Electrical on

Soon after delivery.

Rough-in plumbing

Completed Aug 2025

Plumbing complete

October? Includes three bathrooms, a laundry room, a kitchen and a kitchenette. 

HVAC Install

Soon after delivery. We need this ASAP after the building is delivered so we can work inside the cabin in the winter. 

Final Inspection

October? 

Electrical Finished

October? 

Cabinets installed

November? 

Basement walls

Winter 2026

Basement floor

Winter 2026

Start taking bookings

Winter 2026 (Maybe February?)

Furniture

Spring 2026

Landscaping

April 2026

Grand opening

Target: May 2026. 

First Guests

Target: Memorial Day, 2026. 

© 2025 by Eagles Rest Ministries Birchwood, LLC. Powered and secured by Wix

bottom of page