Sycamore Cabin Building Progress
Click the first photo below to open the full gallery and view our construction timeline.

2025-07-06 15.39_edited


2025-09-22 08.14.37 (Medium)

2025-07-06 15.39_edited
Land Survey
Completed 2019
Septic and water connections
Provided September 2021
Electrical supply
Provided May 2024
Drawings
Completed March 2025
Contractor bids
Completed May2025
Building Permit
Granted June 2025.
Trees down
Started July 3, 2025
Driveway
Started July 3, 2025
Excavation
Started July 6, 2025​
Concrete
Concrete footings and walls are up as of July 15, 2025.
Start of build
Schrock's Hilly Acres began on July 30, 2025
Rough-in electrical
On-site at Schrock's Hilly Acres, August/September.
Build complete
Scheduled for September 10, 2025.
Delivery Scheduled
Scheduled for September 11, 2025.
Delivery
Schrock's Hilly Acres estimate September
Electrical on
Soon after delivery.
Rough-in plumbing
Completed Aug 2025
Plumbing complete
October? Includes three bathrooms, a laundry room, a kitchen and a kitchenette.
HVAC Install
Soon after delivery. We need this ASAP after the building is delivered so we can work inside the cabin in the winter.
Final Inspection
October?
Electrical Finished
October?
Cabinets installed
November?
Basement walls
Winter 2026
Basement floor
Winter 2026
Start taking bookings
Winter 2026 (Maybe February?)
Furniture
Spring 2026
Landscaping
April 2026
Grand opening
Target: May 2026.
First Guests
Target: Memorial Day, 2026.